Project Financials and Accounting

Earned Value Calculation – 3 Common Methods

Earned Value Calculation is done by comparing the planned budget and scheduled work of a project to the actual costs incurred and work completed as the project progresses. Earned Value (EV) estimation provides valuable insight as to whether the project is on time and within budget.

Earned value calculations are the foundational metrics of Earned Value Analysis (EVA). EVA is crucial to accurately measuring current project performance and forecasting their results.

Most companies do not do EVA or they do it infrequently simply because it is too difficult to consolidate and manipulate the data required to do the calculation. Learn more about how Project Business Automation creates a fully integrated and automated Earned Value Management System.

To do an earned value calculation you must choose a method or rule for how progress will be tracked and measured. We call these “earning principles”. I will focus on three common earning principles in this article, what they are, how they are computed and why and when to use them.

Estimate at Completion Earned Value Calculation

Estimate at Completion (EAC) is the most versatile and frequently used earned value principle. EAC Includes all project budget positions, including labor, materials, equipment and expenses.

EAC is calculated by adding actual costs to the estimate to complete (ETC). EAC can be established on an ongoing basis as task owners report their actual costs and then estimate how much work/costs are required to complete their tasks.

Earned Value is then calculated based on actual costs out of Estimate at Completion (i.e. cost incurred to date out of expected cost at project completion).

Here is an example using EAC:

If we look at the highlighted line in this costing sheet we see that line 1.1 Design is using the EAC EVA principle. We can see that the EAC completion column says that the task is complete (100%), so the earned value is 100% earned as well (EVA Completion). In the Actual to date column we see that $4,250 was spent on this task, while the budget (BAC) and Planned value were $4000. Therefore, we had a Cost variance of $250. Then if you look at the Schedule Performance Index we completed the work on time, but the Cost Performance Index shows that we were over budget.

Here is another example:

If we look at line 1.4 we can see that EAC and EVA completion are at 43.15% with Actual costs being $21,250. Our budget (BAC) for this task is $48,200 total, and at this point in the schedule our Planned value is $21,600. However, our EAC says now we are going to spend $49,250 on this task and we are only 43.15% complete, which means our earned value is $20,797. As a result, we can see our Schedule variance says we are behind schedule and our Cost variance tells us we are over budget.

EAC is the simplest principle to use as the value is automatically generated as part of the month-end (reforecasting) process.

Deliverables

Using Deliverables to calculate earned value is based on deliverables reported as completed out of total budgeted deliverables. The method requires you to enter quantity budgets against your Cost Breakdown Structure (CBS).

For example, a deliverable might be to install 1000 feet of piping. If 100 feet of piping has been installed, completion is calculated at 10%. This method is commonly used as progress tracking in construction industries. It is sometimes called “quantity reporting” or “production units”.

Here is a Deliverables example:

If we look at the highlighted row 2.1.1 we can see it is using the Deliverables EVA principle. The Div completion column tells us we are 97.62% complete on this task. Turned into dollars, we see that our Actual cost to date is $224,300. At 97.62% complete, we should have spent only $221,546 (Earned value). Additionally, at this point the task should be completed and total Planed Value is $226,950. If we look at the variance columns, we can see that we are both behind schedule and over budget on this task.

Completed Work

The Completed Work earning principle is based on actual work out of remaining work + actual work (measured in hours). In basic terms, it is the hours spent to date out of expected hours required in total at task/project completion.

For example, 100 hours are required for task X over a period of 4 weeks. At 2 weeks 30 hours were completed while 70 remain, 30% of the work is done while the planned completion rate was 50%. Assuming hours = cost, we are behind schedule. If a new estimate of 80 hours would be required to complete the task, then we are 10 hours over budget as well.

Completed Work earned value calculations are typically used in labor intensive fields. Professional Services companies tend to use this principle when computing earned value.

Earned Value Management

Most companies do not do EVA or they do it infrequently simply because it is too difficult to consolidate and manipulate the data required to do the calculation. That is unfortunate because it is a powerful tool for meaningfully understand the state of your projects and thereby your business.

The key to making EVA a regular part of your routine is to integrate all your data into one Earned Value Management System. That means that your processes and workflows are managed in that system as well. When that happens, EVA can be done automatically.

Project Business Automation provides that fully integrated, comprehensive business system for project-based companies.

Learn more about how PBA from Adeaca can automate your Earned Value Analysis.

Henrik Lerkenfeld

Henrik is Adeaca's Head of Product Development. Henrik has deep roots in Microsoft Dynamics, having been part of the original Axapta ecosystem and Microsoft’s team after it was acquired. His knowledge of project industries and his systematic process design approach is a crucial component of Adeaca’s customers' success.

Recent Posts

4 Steps to Get Started with Project Business Transformation

In today’s increasingly complex project environments, businesses are facing unprecedented challenges in delivering projects on time, within budget, and according…

3 months ago

Why Project Business Transformation: Unlocking the Benefits and Value

Project Business Transformation reduces risk, increases efficiency, and enhances decision-making in your project organization. Project Business Automation is a new…

3 months ago

What is Project Business Transformation?

Project Business Transformation is a strategic digital transformation initiative designed to fundamentally change how projects are managed and delivered in…

3 months ago

AI in Project Management: Cutting through the Hype

There is so much hype around the use of AI in project management. What is the reality? Join Chief Category…

8 months ago

Is Your Project Business Ready for Risk?

In the dynamic landscape of project-driven enterprises, risk is omnipresent. As projects become integral components of your business strategy, the…

1 year ago

How to Manage Projects by Exception

Management by exception is a method of business management that focuses on identifying and managing cases that deviate from the…

1 year ago